12 workers can do a peice of work in 20 days. How many workers should be added to complete work in 16 days?​

Respuesta :

atchleyamirah69
atchleyamirah69 atchleyamirah69
  • 01-04-2021
3 workers

if 12 workers can do a piece of work in 20 days, then one person can do it in 240 days. 240/16 is 15. That is the number of workers that you need in total to it in 16 days. Since the question ask how many more workers,
15 - 12 = 3 more workers.
Answer Link

Otras preguntas

fort knox holds 147,300,000 onces of gold. write the number that is one million more
The committee discussed (its, their) personal goals for the coming year.
12 posters for 36 student;21 poster for 63 students
when i double my number and add eight i get my number plus twelve whats mynumber
what is the estimate of 324867 plus 6233
what are two acent democracy that helped form amica today
how do I write 119,000,003 in word form
Lisa had 3 dollars. she went to the bank and exchanged the 3 dollars for 30 dimes. Describe the relationship between the value of a dollar and the value of a
How to do criss cross multiplication
Driving while wearing headphones or headsets a. is not dangerous, because you can still see everything around you b. is more entertaining than listening to th