When looking at a program board at the end of program increment (PI) planning, what does it mean when a feature is placed in a team's swim lane with no strings

Respuesta :

IfeanyiEze8899 IfeanyiEze8899
  • 04-01-2021

Answer:

It simply means that other teams can independently complete the feature.

Explanation:

PI or program increment is a planning interval during which an agile release train (ART) plans and produces working and tested software and systems. It takes a duration of 8 to 12 weeks

Agile teams can access and independently complete various ARTs found in their swim lanes with no strings.

Answer Link

Otras preguntas

in what way is a gene pool representative of a population
What is 0.75 as a fraction in simplist form
How do you pronounce the letter "X" in Spanish?
WHICH EXPRESSION IS EQUIVALENT TO SIN 22 COS 18 + COS 22 SIN 18?
mike constructed a closed box that measures 2.5 feet long by 3 feet wide by 1.5 feet high. what is the total area of the material mike needs to construct the bo
THE EXPRESSION (TAN THETA) (CSC THETA) IS EQUAL TO?
A person sees a ball and kicks it, in part because of actions of the nervous system. Using the parts of the nervous system listed bellow, describe the path of n
What is does the phrase foe to ambition.
which is longer 635 millimeters or 535 centimeters ?
when gravity causes a huge amounts of rock or soil to be carried down a slope this form of erosion is referred to as a