To complete a job a crew of 8 people needs 18 days. How long will the same job be finished if the crew will have 9 people?

Respuesta :

rockyrules789 rockyrules789
  • 01-11-2019

Answer:

16

Step-by-step explanation:

.

Answer Link
lajfoaofje lajfoaofje
  • 27-06-2020

Answer:

16

Step-by-step explanation:

Answer Link

Otras preguntas

The Frederick country fair costs $15.00 to get in and $2.50 per ride, while the Montgomery County Fair costs $10.00 to get and $3.00 per ride. Which equations c
Which of these statements describe the working and living conditions of most enslaved people? Check all of the boxes that apply. A—They faced long days, ha
Ross is conducting an investigation in which he has grown three bean plants in three different pots. Each pot is similar in size and contains the same amount an
Porque se mencionan paises como francia y Grecia en el reportage
The Supremes song that Lily hears makes her think: “There’s nothing like a song about lost love to remind you how everything precious can slip from the hinges w
what if i forget my password to my brainly account how will i get my login
Amina posts three large letters the postage is the same for each letter she pays with a £20 note her change is £14.96 what is the cost of posting one letter?
If the top of a rectangular table has an area of 35in^2, and its dimensions have a sum of 12, what are the dimensions?
The perimeter of the shape is ______ feet.
Complete the passage to summarize factors affecting the speed of a wave. The material or substance that a wave moves through is called a The medium affects the